Pharma Installation Qualification from Protocol to Approval

Part 9

The required lifecycle sequence is:

URS → Risk Assessment → DQ → FAT → SAT → IQ → OQ → PQ → Qualification Summary → GMP Release

The fundamental IQ question is:

Has the equipment/system been installed correctly at its intended location in accordance with the approved design, manufacturer’s recommendations, applicable GMP requirements, and controlled engineering documentation?


9.1 What Is Installation Qualification?

Installation Qualification (IQ) is documented verification that the installed facilities, systems, utilities, equipment, instrumentation, computerized components, and associated supporting elements conform to approved specifications and installation requirements.

IQ establishes the documented installed baseline.

It confirms, as applicable:

  • the correct equipment was installed;
  • it is installed at the correct location;
  • major components are correct;
  • product-contact components are appropriate;
  • materials of construction are documented;
  • utilities are correctly connected;
  • instruments are installed and calibrated;
  • electrical installation is correct;
  • software/firmware versions are identified;
  • PLC/HMI/SCADA components are documented;
  • safety devices are installed;
  • required documentation exists;
  • maintenance/calibration requirements are established.

9.2 Purpose of IQ

The purpose of IQ is not merely to prove that equipment is physically present.

IQ should establish:

The final installed configuration is known, documented, traceable, and suitable to proceed to operational testing.

A robust IQ creates a controlled baseline for:

OQ → PQ → Routine Operation → Maintenance → Calibration → Change Control → Periodic Review


9.3 IQ Position in the Lifecycle

User Requirement Specification
             ↓
      Risk Assessment
             ↓
    Design Qualification
             ↓
            FAT
             ↓
          Shipment
             ↓
     Site Installation
             ↓
            SAT
             ↓
     ┌────────────────┐
     │       IQ       │
     └────────────────┘
             ↓
            OQ
             ↓
            PQ
             ↓
 Qualification Summary
             ↓
       GMP Release

IQ therefore converts:

Approved Design

into

Verified Installed Configuration


9.4 IQ vs SAT

SAT and IQ may contain similar activities, but their purposes differ.

SATIQ
Site acceptance activityFormal qualification activity
Confirms delivery/site functionalityEstablishes qualified installed baseline
Focuses on transport/site changesFocuses on approved installation requirements
Often vendor/project drivenUsually qualification/PQS driven
Supports readiness for IQ/OQSupports progression to OQ

Where suitable SAT evidence is leveraged into IQ, the rationale should be documented.


9.5 IQ vs OQ

IQ asks:

What has been installed?

OQ asks:

Does the installed system operate correctly?

Example:

IQ

Verify pressure transmitter:

  • tag;
  • manufacturer;
  • model;
  • range;
  • installation;
  • calibration status.

OQ

Challenge the associated:

  • measurement;
  • alarm;
  • control;
  • interlock;
  • operating range.

9.6 Risk-Based IQ

Not every component requires the same qualification depth.

IQ scope should consider:

  • GMP impact;
  • product impact;
  • criticality;
  • quality risk;
  • process function;
  • data-integrity impact;
  • safety impact;
  • maintenance/calibration requirements.

High-risk components generally require stronger objective evidence.


9.7 IQ Inputs

Typical IQ inputs include:

  • approved URS;
  • qualification plan/VMP;
  • system-impact assessment;
  • quality risk assessment;
  • DQ;
  • FAT report;
  • SAT report;
  • approved drawings;
  • as-built drawings;
  • P&IDs;
  • equipment specifications;
  • vendor manuals;
  • component lists;
  • instrument lists;
  • calibration certificates;
  • material certificates;
  • electrical drawings;
  • software documentation;
  • network architecture;
  • spare-parts list;
  • maintenance requirements.

9.8 IQ Prerequisites

Before IQ execution, confirm as applicable:

  • □ IQ protocol approved
  • □ Equipment installed
  • □ SAT status acceptable
  • □ Critical SAT items closed
  • □ Utilities connected
  • □ Equipment identification assigned
  • □ Drawings available
  • □ Instrument list available
  • □ Calibration records available
  • □ Material certificates available
  • □ Electrical installation substantially complete
  • □ Software/configuration baseline identified
  • □ Safety systems installed
  • □ Required test instruments available
  • □ Test instruments calibrated
  • □ Open project items reviewed
  • □ Relevant personnel trained for protocol execution

9.9 Recommended IQ Protocol Structure

A comprehensive IQ protocol may contain:

1. Document Control

  • document title;
  • IQ number;
  • revision;
  • project number;
  • equipment/system ID;
  • location.

2. Approval

  • prepared by;
  • reviewed by;
  • approved by.

3. Objective

4. Scope

5. System Description

6. Responsibilities

7. References

8. Definitions and Abbreviations

9. Prerequisites

10. Test Equipment

11. Equipment Identification

12. Installation Verification

13. Major Component Verification

14. Product-Contact Component Verification

15. Material-of-Construction Verification

16. Surface-Finish Verification

17. Utility Verification

18. Piping/P&ID Verification

19. Electrical Verification

20. Instrumentation Verification

21. Calibration Verification

22. PLC/HMI/SCADA Hardware Verification

23. Software/Firmware Verification

24. Network/Interface Verification

25. Safety-System Verification

26. Documentation Verification

27. Spare-Parts Verification

28. Lubricant Verification

29. Preventive-Maintenance Requirements

30. Calibration Requirements

31. SOP Requirements

32. Training Requirements

33. As-Built Documentation

34. Deviations

35. Open Items

36. Traceability

37. IQ Summary

38. OQ Readiness

39. Approval


9.10 Standard IQ Test Format

Every significant IQ test should follow a consistent structure.

Test ID

Unique test number.

Test Title

Clear description.

Objective

What is being verified?

Prerequisites

What must exist before execution?

Test Method

How will verification be performed?

Expected Result

What result is expected?

Actual Result

What was actually observed?

Acceptance Criteria

What determines Pass/Fail?

Evidence

What objective documentation supports the result?

Status

PASS / FAIL / NOT APPLICABLE

Executed By

Name/signature/date.

Reviewed By

Name/signature/date.


9.11 Equipment Identification

The first IQ activity should establish equipment identity.

Verify:

  • equipment name;
  • equipment ID/tag;
  • manufacturer;
  • model;
  • serial number;
  • location;
  • project number where applicable.

Example:

AttributeRequirementActualStatus
EquipmentTablet Compression Machine_____
TagApproved ID_____
ManufacturerApproved Vendor_____
ModelApproved Model_____
Serial NumberVendor Record_____
LocationApproved Room_____

9.12 Equipment Installation

Verify installation against approved:

  • GA drawing;
  • layout;
  • manufacturer’s instructions;
  • design specifications.

Consider:

  • location;
  • orientation;
  • anchoring;
  • leveling;
  • clearance;
  • operator access;
  • maintenance access;
  • cleaning access.

9.13 Example IQ Test — Installation

Test ID

IQ-INS-001

Objective

Verify that the equipment is installed at the approved location and orientation.

Prerequisites

Approved equipment layout available.

Test Method

Compare installed equipment position and orientation with the approved/as-built layout.

Expected Result

Equipment corresponds to the approved installation arrangement.

Actual Result


Acceptance Criteria

No unexplained discrepancy exists between installed configuration and approved/as-built documentation.

Evidence

Layout drawing number/revision and field inspection record.

Status

PASS / FAIL


9.14 Major Component Verification

Identify significant equipment components.

For a tablet compression machine:

  • main frame;
  • turret;
  • compression rollers;
  • feeder;
  • hopper;
  • lubrication system;
  • motor;
  • drive;
  • reject mechanism;
  • control panel;
  • PLC;
  • HMI.

9.15 Component Verification Table

ComponentManufacturerModelSerial No.Design ReferenceActualStatus
Main Motor
Drive
PLC
HMI
Lubrication Pump

The required detail should reflect component criticality.


9.16 Product-Contact Components

Product-contact components require particular attention because they can directly influence product quality.

Verify as applicable:

  • identification;
  • material;
  • surface condition;
  • installation;
  • certification;
  • cleanability.

Examples:

  • hopper;
  • feeder;
  • product chute;
  • transfer pipe;
  • mixing vessel;
  • spray nozzle;
  • discharge assembly.

9.17 Material of Construction

IQ should verify specified material-of-construction requirements using appropriate evidence.

Potential evidence:

  • material certificates;
  • certificates of conformity;
  • vendor material list;
  • fabrication records;
  • approved drawings;
  • component identification.

Do not automatically assume that visual appearance proves stainless-steel grade.


9.18 Example Material Verification

ComponentRequirementCertificateActual MaterialStatus
HopperApproved MOCMTC-001_____
FeederApproved MOCMTC-002_____
Product ChuteApproved MOCMTC-003_____

The acceptance criterion should correspond to the approved design requirement.


9.19 Surface Finish

Where surface finish is a specified GMP requirement, IQ should verify appropriate evidence.

Potential methods include:

  • supplier certificate;
  • fabrication record;
  • approved surface-finish documentation;
  • direct measurement where justified.

Do not introduce an arbitrary universal roughness value if the URS/design does not establish one.


9.20 Gaskets and Seals

Where GMP significant, verify:

  • material;
  • identification;
  • compatibility;
  • installation;
  • certificates where required.

Typical examples include:

  • silicone;
  • EPDM;
  • PTFE;
  • other approved elastomers.

Selection should reflect the approved process and cleaning requirements.


9.21 Utility Verification

Verify all required utilities.

Potential utilities include:

  • electricity;
  • compressed air;
  • vacuum;
  • dust extraction;
  • nitrogen;
  • Purified Water;
  • WFI;
  • clean steam;
  • chilled water;
  • process gases.

9.22 Utility IQ Table

UtilityRequirementConnectionActualStatus
ElectricalApproved specificationVerified_____
Compressed AirApproved pressure/qualityVerified_____
VacuumApproved requirementVerified_____
Dust ExtractionApproved requirementVerified_____

IQ should distinguish between:

Utility connection verification

and

Utility system qualification/performance

when the utility itself is separately qualified.


9.23 Piping Verification

Where piping exists, verify:

  • line identification;
  • material;
  • size;
  • routing;
  • flow direction;
  • valves;
  • instruments;
  • connection;
  • slope where relevant;
  • drainability where relevant.

9.24 P&ID Verification

Perform field verification against the approved/as-built P&ID.

A typical method:

  1. Start from defined system boundary.
  2. Follow each process/utility line.
  3. Verify equipment.
  4. Verify valves.
  5. Verify instruments.
  6. Verify flow direction.
  7. Record discrepancies.
  8. Update as-built documentation where necessary.

9.25 P&ID Walkdown

A P&ID walkdown should establish:

Drawing = Actual Installed System

Any discrepancy should be:

  • documented;
  • assessed;
  • corrected in field or drawing;
  • incorporated into controlled as-built documentation.

9.26 Electrical Verification

Verify applicable:

  • power supply;
  • voltage;
  • phase;
  • frequency;
  • control panel;
  • breakers;
  • fuses;
  • cables;
  • wiring;
  • terminal identification;
  • motors;
  • drives;
  • earthing;
  • electrical drawings.

9.27 Electrical Panel Verification

Example:

ComponentDesign RequirementInstalledStatus
Main IsolatorSpecified rating_____
PLC Power SupplyApproved model_____
DriveApproved model_____
Safety RelayApproved model_____
Circuit ProtectionApproved_____

9.28 Earthing

Where applicable, verify:

  • protective earthing;
  • bonding;
  • designated earth points;
  • installation condition.

Measurement requirements should follow applicable engineering/site standards and approved specifications.


9.29 Instrumentation Verification

Create or verify the instrument register.

For each critical instrument document as applicable:

  • tag;
  • description;
  • manufacturer;
  • model;
  • serial number;
  • range;
  • accuracy;
  • location;
  • calibration status.

9.30 Instrument Register Example

TagParameterManufacturerModelRangeCalibration DueStatus
PT-101Pressure
TT-101Temperature
ST-101Speed
LC-101Load/Force

9.31 Calibration Verification

For GMP-relevant instruments, verify:

  • calibration certificate;
  • instrument identity;
  • calibration range;
  • calibration points where relevant;
  • result;
  • calibration date;
  • due date;
  • reference standard traceability as applicable.

9.32 Calibration Range vs Operating Range

A critical review is:

Does calibration adequately cover the intended operating/qualification range?

Example:

Process operating range:

10–50 units

Calibration performed:

0–100 units

This may be suitable depending on instrument requirements and calibration methodology.

However, calibration evidence should be evaluated against intended use rather than accepted merely because a certificate exists.


9.33 Calibration Status Labels

Verify that instrument status identification is consistent with site procedures.

Typical information may include:

  • instrument ID;
  • calibration date;
  • due date;
  • status.

The controlled calibration system remains the authoritative record according to site procedure.


9.34 Test Instruments Used During IQ

Any measuring instrument used to generate qualification evidence should be appropriately suitable.

Document:

  • instrument name;
  • ID;
  • range;
  • calibration status;
  • due date.

Example:

Test InstrumentIDRangeCalibration DueUsed For
MultimeterElectrical
Pressure GaugeUtility
TachometerSpeed
LevelInstallation

9.35 PLC Hardware Verification

For PLC-controlled equipment verify:

  • manufacturer;
  • PLC model;
  • CPU;
  • I/O modules;
  • communication modules;
  • power supply;
  • cabinet location.

Compare against:

  • approved design;
  • FAT baseline;
  • final hardware list.

9.36 HMI Hardware Verification

Document:

  • manufacturer;
  • model;
  • serial number;
  • screen type;
  • location;
  • communication interface.

The HMI should be uniquely associated with the qualified system.


9.37 SCADA Hardware

Where applicable, verify:

  • workstation;
  • server;
  • client;
  • network hardware;
  • interface hardware.

For virtualized environments, physical-server verification may be replaced or supplemented by appropriate infrastructure/configuration evidence according to the validation strategy.


9.38 Software Verification

IQ should identify installed software.

Potential examples:

  • PLC program;
  • HMI application;
  • SCADA application;
  • database;
  • firmware;
  • operating system;
  • supporting software.

9.39 Software Version Register

SoftwareFAT VersionApproved VersionInstalled VersionStatus
PLC Program_______________
HMI Application_______________
SCADA_______________
Firmware_______________
OS_______________

Unexplained differences require assessment.


9.40 Software Baseline

IQ should establish the approved software/configuration baseline before OQ.

The baseline may include:

Software Name + Version + Build + Configuration + Backup + Checksum/Hash where used by the site’s control strategy

The exact method depends on the system and approved procedures.


9.41 Firmware

Firmware can affect system functionality and should be documented where relevant.

Examples:

  • PLC CPU firmware;
  • HMI firmware;
  • drive firmware;
  • instrument firmware;
  • communication-module firmware.

Not every firmware version is necessarily GMP critical, but relevant versions should be identified based on risk.


9.42 Network Verification

For network-connected systems verify as applicable:

  • network connection;
  • IP address;
  • hostname;
  • subnet;
  • VLAN;
  • server;
  • communication port;
  • time server;
  • domain;
  • firewall arrangements.

Sensitive cybersecurity details should remain controlled according to site procedures.


9.43 Network Architecture

Example:

Tablet Compression Machine
          │
         PLC
          │
         HMI
          │
   Industrial Network
          │
        SCADA
          │
       Historian
          │
      Site Server

IQ establishes that the required architecture is installed.

OQ/CSV subsequently demonstrates applicable functionality.


9.44 Communication Interfaces

Identify interfaces with:

  • MES;
  • LIMS;
  • SCADA;
  • historian;
  • ERP;
  • BMS;
  • EMS;
  • printers;
  • peripheral machines.

Document interface type and configuration where GMP relevant.


9.45 Safety Device Installation

IQ should verify installation of applicable safety devices.

Examples:

  • emergency stops;
  • guards;
  • guard switches;
  • safety relays;
  • pressure relief devices;
  • overload protection;
  • safety sensors.

IQ confirms installation.

OQ challenges functionality.


9.46 Emergency Stops

Verify:

  • number;
  • location;
  • identification;
  • physical installation;
  • accessibility.

Example:

E-Stop IDLocationRequiredInstalledStatus
ES-01Operator sideYesYesPass
ES-02Rear sideYesYesPass

9.47 Guards

Verify:

  • required guards installed;
  • correct location;
  • secure mounting;
  • safety-switch installation where applicable.

Functional challenge is generally addressed during OQ/SAT as appropriate.


9.48 Pressure-Relief Devices

Where relevant, document:

  • device ID;
  • location;
  • set pressure;
  • certification;
  • installation orientation;
  • discharge arrangement.

This can be particularly important for:

  • pressure vessels;
  • steam systems;
  • compressed-gas systems.

9.49 Lubricants

Lubricants should be reviewed where they can affect equipment reliability or potentially contact product.

Document:

  • lubricant name;
  • manufacturer;
  • grade;
  • application point;
  • food/pharmaceutical suitability where required;
  • vendor recommendation.

9.50 Lubricant Register

Lubrication PointLubricantGradeProduct Contact RiskStatus
Main bearing__________No
Feeder drive__________No
Potential incidental-contact point__________Assess

Selection should be justified by intended application.


9.51 Spare Parts

IQ should verify availability or identification of critical spare parts as required by the project strategy.

Examples:

  • sensors;
  • seals;
  • PLC modules;
  • HMI;
  • drives;
  • motors;
  • filters;
  • product-contact parts.

The objective is lifecycle maintainability rather than simply counting every spare delivered.


9.52 Critical Spare-Parts Register

SparePart NumberCriticalityQuantityStorage Location
PLC ModuleHigh
HMIHigh
SensorHigh
Seal KitMedium

9.53 Vendor Documentation

Verify availability of required vendor documentation.

Potential documents include:

  • operation manual;
  • maintenance manual;
  • installation manual;
  • spare-parts manual;
  • troubleshooting guide;
  • calibration instructions;
  • electrical drawings;
  • pneumatic drawings;
  • software manuals.

9.54 Engineering Drawings

Typical IQ-controlled drawings may include:

  • GA drawing;
  • layout;
  • P&ID;
  • piping drawings;
  • electrical drawings;
  • pneumatic diagrams;
  • control-panel drawings;
  • network architecture;
  • instrument diagrams.

The applicable drawings should represent the final installed configuration.


9.55 As-Built Documentation

One of the most important IQ concepts is:

Qualification should represent what was actually installed—not merely what was originally designed.

Therefore, relevant documents should reach an appropriate as-built state.


9.56 Design vs As-Built

Example:

Design

Valve V-102 shown upstream of instrument PT-101.

Actual Installation

Valve relocated downstream during installation.

Even if technically acceptable, the drawing is no longer accurate.

Required process:

Identify Difference → Assess → Approve → Update Drawing → Verify As-Built


9.57 Preventive Maintenance

Before qualification completion, the organization should understand the equipment’s preventive-maintenance requirements.

Review:

  • vendor recommendations;
  • lubrication;
  • inspection frequency;
  • replacement intervals;
  • safety checks;
  • filters;
  • belts;
  • seals;
  • critical components.

9.58 PM Assessment

A practical PM table:

ComponentVendor RecommendationSite PM RequiredFrequencyProcedure/Task
Main DriveInspectYesTBD/Approved
Lubrication SystemInspectYes
Safety GuardsInspectYes
FiltersReplaceYes

Final frequency should be established through the site’s approved maintenance system.


9.59 Calibration Program

GMP-relevant instruments should be incorporated into the site’s calibration program where required.

Document:

  • instrument ID;
  • criticality;
  • calibration frequency;
  • range;
  • tolerance;
  • responsible department.

The initial calibration evidence should connect to ongoing lifecycle control.


9.60 SOP Requirements

IQ should identify SOPs required before routine operation.

Examples:

  • equipment operation;
  • cleaning;
  • assembly/disassembly;
  • changeover;
  • calibration;
  • maintenance;
  • backup/restore;
  • user administration;
  • alarm handling;
  • audit-trail review where applicable.

Not all SOPs necessarily need final approval before IQ execution, but required readiness gates should be defined before GMP release.


9.61 Training Requirements

Identify personnel requiring training.

Potential groups:

  • operators;
  • supervisors;
  • maintenance;
  • engineering;
  • QA;
  • validation;
  • automation;
  • administrators.

Training should be completed before personnel perform activities for which qualification or GMP procedures require demonstrated readiness.


9.62 Training Matrix

RoleOperationCleaningMaintenanceSystem AccessAudit Trail
OperatorAs applicable
Supervisor
MaintenanceLimitedLimited
AdministratorSystemAs applicable

Actual requirements depend on system intended use.


9.63 Equipment Cleaning Readiness

IQ may verify installation-related cleaning prerequisites:

  • removable components;
  • cleaning access;
  • cleaning tools;
  • drainage;
  • cleaning-agent compatibility;
  • cleaning instructions.

Cleaning validation itself is a separate lifecycle activity where required.


9.64 Equipment Status Identification

Following installation, equipment should be controlled according to site procedures.

Potential status examples:

  • Under Installation;
  • Under Qualification;
  • Qualified;
  • Out of Service.

Status controls help prevent unintended GMP use before qualification completion.


9.65 Equipment Logbook

Where required, establish the equipment logbook or equivalent controlled electronic record.

It may capture:

  • operation;
  • cleaning;
  • maintenance;
  • breakdowns;
  • calibration;
  • qualification;
  • significant interventions.

The exact requirements should follow the site’s documentation system.


9.66 IQ Deviations

An IQ deviation may arise when:

  • wrong component installed;
  • material certificate missing;
  • utility does not meet specification;
  • instrument range differs;
  • calibration expired;
  • drawing differs from installation;
  • software version differs;
  • required safety device is missing.

These discrepancies should not simply be overwritten in the protocol.


9.67 IQ Deviation Lifecycle

Unexpected IQ Result
        ↓
Record Deviation
        ↓
Assess GMP / Quality Impact
        ↓
Investigate Cause
        ↓
Determine Corrective Action
        ↓
Assess Other Tests / Systems
        ↓
Implement Correction
        ↓
Approve Retest
        ↓
Retest
        ↓
Close Deviation

9.68 Example IQ Deviation

Requirement

Pressure transmitter range:

0–6 bar

Installed

0–10 bar

Do not immediately conclude:

“Acceptable because 10 bar includes 6 bar.”

Assess:

  • required operating range;
  • measurement accuracy;
  • resolution;
  • calibration;
  • alarm/control requirements;
  • DQ/design specification;
  • process risk.

Possible outcomes:

  • accept with technical justification;
  • revise design documentation;
  • replace instrument.

9.69 Missing Material Certificate

Suppose product-contact component certification is missing.

Possible process:

  1. Record discrepancy.
  2. Identify component.
  3. Contact supplier.
  4. Obtain certificate or equivalent evidence.
  5. Verify linkage between certificate and component.
  6. Assess adequacy.
  7. Close discrepancy.

Do not create unsupported retrospective certification.


9.70 Drawing Discrepancy

Suppose field installation differs from P&ID.

Do not alter the executed IQ record to make it appear that the drawing was always correct.

Instead:

Record discrepancy → Assess actual installation → Determine correct configuration → Update controlled drawing → Verify revised as-built drawing → Close

This preserves data integrity.


9.71 IQ Open Items

Open items may be classified based on risk.

Critical

Prevents progression to OQ.

Major

May allow limited progression only with approved justification.

Minor

Can potentially be closed before final qualification release.

Example:

ItemDescriptionCriticalityRequired BeforeOwnerStatus
01Critical instrument calibration missingCriticalOQEngineeringOpen
02Final drawing pendingMajorIQ closureVendorOpen
03Spare label missingMinorProject closureVendorOpen

9.72 IQ Acceptance Criteria

Overall IQ acceptance should establish that:

  • required equipment/components are correctly installed;
  • critical materials are appropriately documented;
  • utilities are correctly connected;
  • required instruments are installed and appropriately calibrated;
  • electrical installation is acceptable;
  • software/hardware baseline is established;
  • required safety devices are installed;
  • required documentation is available;
  • critical discrepancies are resolved;
  • outstanding items are appropriately assessed;
  • the system is ready for OQ.

9.73 IQ Summary Report

The IQ summary should contain:

  1. Objective
  2. Scope
  3. Protocol executed
  4. Equipment identification
  5. Tests performed
  6. Test results
  7. Deviations
  8. Retests
  9. Open items
  10. Calibration status
  11. Documentation status
  12. Software/configuration baseline
  13. As-built status
  14. Maintenance/calibration readiness
  15. Overall conclusion
  16. OQ readiness
  17. Approval

9.74 Example IQ Summary Table

IQ SectionStatusComments
Equipment IdentificationPassVerified
InstallationPassAs-built configuration confirmed
Product-Contact ComponentsPassDocumentation available
MaterialsPassCertificates verified
UtilitiesPassConnections verified
ElectricalPassInstallation acceptable
InstrumentsPassCritical instruments identified
CalibrationPassCurrent
PLC/HMIPassBaseline established
NetworkPassConfiguration documented
Safety DevicesPassInstalled
DocumentationConditionalMinor open item
PM/Calibration SetupPassRequirements identified

9.75 IQ to OQ Readiness Gate

Before OQ begins, confirm:

  • □ IQ executed
  • □ Critical IQ tests passed
  • □ Critical deviations closed
  • □ Required utilities available
  • □ Critical instruments calibrated
  • □ Safety systems installed
  • □ Software baseline controlled
  • □ Required configuration established
  • □ Critical drawings available
  • □ Test equipment available
  • □ OQ protocol approved
  • □ Remaining open items assessed for OQ impact

9.76 Worked Example — Tablet Compression Machine IQ

The tablet compression machine provides a useful complete example.

Equipment Identification

Verify:

  • manufacturer;
  • model;
  • serial number;
  • equipment tag;
  • room/location.

Major Components

Verify:

  • hopper;
  • feeder;
  • turret;
  • compression rollers;
  • motor;
  • drive;
  • lubrication system;
  • reject mechanism;
  • control panel;
  • PLC;
  • HMI.

Product-Contact Components

Verify:

  • hopper;
  • feeder;
  • turret/product path as applicable;
  • discharge chute;
  • reject chute.

Utilities

Verify:

  • electricity;
  • compressed air;
  • dust extraction;
  • vacuum where applicable.

Instrumentation

Verify:

  • compression-force sensors;
  • speed measurement;
  • pressure instruments;
  • proximity sensors;
  • reject sensors.

Automation

Verify:

  • PLC hardware/version;
  • HMI hardware/version;
  • software baseline;
  • network;
  • interfaces.

Safety

Verify installation of:

  • guards;
  • emergency stops;
  • safety switches;
  • safety relays.

9.77 Compression Machine IQ Matrix

RequirementIQ VerificationEvidence
Correct machineManufacturer/model/serialNameplate
Approved locationLayout verificationAs-built layout
Product-contact MOCCertificate reviewMTC/CoC
Compression systemComponent verificationVendor documentation
FeederIdentificationComponent record
MotorRating/modelNameplate
Compressed airConnection verificationUtility record
Dust extractionConnectionP&ID/layout
InstrumentsTag/range/calibrationCertificates
PLCHardware/versionSystem record
HMIHardware/versionSystem record
NetworkConfigurationNetwork record
GuardsInstallationInspection
E-stopsInstallationInspection
ManualsAvailabilityDocument register
PMRequirements identifiedPM assessment

9.78 Example Full IQ Test — Compression Force Sensor

Test ID

IQ-INS-014

Title

Compression Force Sensor Installation and Calibration Verification

Objective

Verify that the compression-force measurement system is installed in accordance with approved specifications and has appropriate calibration status.

Prerequisites

  • equipment installation complete;
  • approved instrument list available;
  • calibration certificate available.

Test Method

  1. Identify compression-force sensor.
  2. Record manufacturer.
  3. Record model.
  4. Record serial number.
  5. Verify installation location.
  6. Verify measurement range.
  7. Review calibration certificate.
  8. Verify calibration status.
  9. Compare against approved instrument specification.

Expected Result

Installed sensor corresponds to the approved specification and possesses acceptable calibration status.

Actual Result


Acceptance Criteria

The installed sensor shall be identifiable, appropriately installed, within the approved specification and supported by acceptable calibration evidence.

Evidence

  • instrument datasheet;
  • calibration certificate;
  • instrument register.

Status

PASS / FAIL

Executed By


Reviewed By



9.79 Example Full IQ Test — PLC/HMI

Test ID

IQ-AUT-001

Objective

Verify installed PLC and HMI hardware/software identification against the approved system baseline.

Method

Record:

  • PLC manufacturer;
  • PLC model;
  • CPU;
  • firmware;
  • PLC application version;
  • HMI manufacturer;
  • HMI model;
  • HMI application version.

Compare with:

  • approved design;
  • FAT baseline;
  • SAT baseline.

Acceptance Criteria

Installed hardware/software shall correspond to the approved configuration or any difference shall have an approved documented disposition.

Evidence

  • hardware inspection;
  • software/version screen;
  • controlled configuration record.

9.80 Example Full IQ Test — Utility Connection

Test ID

IQ-UTL-003

Objective

Verify the compressed-air connection to the equipment.

Method

  1. Identify compressed-air connection.
  2. Verify connection point.
  3. Verify line identification.
  4. Verify approved connection arrangement.
  5. Measure supply pressure where required using an appropriate calibrated instrument.
  6. Record result.

Acceptance Criteria

Compressed-air installation shall conform to approved utility requirements.

Evidence

  • P&ID;
  • utility drawing;
  • measurement record;
  • test-instrument calibration record.

9.81 IQ Traceability

IQ should contribute to the overall traceability matrix.

Example:

URSRiskDQFAT/SATIQOQPQ
URS-001RA-01DQ-01FAT-01IQ-01
URS-012RA-05DQ-04FAT-05IQ-08
URS-025RA-12DQ-09FAT-18/SAT-08IQ-20OQ-15
URS-041RA-21DQ-15FAT-30IQ-25OQ-22

Not every URS needs testing at every lifecycle stage.

The matrix should show where adequate evidence exists.


9.82 Leveraging FAT/SAT Evidence in IQ

Controlled FAT/SAT evidence may potentially support IQ when:

  • the requirement was adequately tested;
  • objective evidence exists;
  • test instruments were appropriate;
  • acceptance criteria were predefined;
  • configuration is unchanged;
  • transportation/installation could not invalidate the evidence;
  • change history is controlled.

The IQ should explicitly reference leveraged evidence.


9.83 Example of Appropriate Leverage

FAT Evidence

Material certificate for a permanently identified product-contact component.

SAT

Component identity verified after delivery.

IQ

References:

  • FAT certificate;
  • SAT identity confirmation.

No scientific value may be gained from requesting another duplicate certificate merely because the lifecycle has reached IQ.


9.84 Example Where FAT Cannot Fully Replace IQ

FAT

PLC hardware verified at vendor.

After FAT

Control panel disconnected, transported, installed and site network connected.

IQ

Still verify:

  • installed PLC identity;
  • hardware configuration;
  • software version;
  • site connection.

The final installed state matters.


9.85 Common IQ Deficiencies

DeficiencyConcern
IQ is only a checklistInsufficient objective evidence
No URS/risk traceabilityQualification disconnected from requirements
Nameplate data missingEquipment identity uncertain
Materials visually assumedMOC not objectively established
Instrument certificate accepted without ID checkCertificate may not belong to installed instrument
Calibration range not reviewedInstrument may be unsuitable
Drawings not field verifiedDocumentation may not reflect installation
Software version omittedComputerized baseline unknown
Network ignoredSite architecture incomplete
SAT evidence duplicated without rationaleInefficient qualification
FAT evidence blindly acceptedInstallation impact ignored
PM/calibration not establishedQualified state difficult to maintain
Open items uncontrolledOQ starts on incomplete system
As-built documentation missingFuture maintenance/change control compromised

9.86 Inspector Perspective

An inspector may ask:

Show me how you verified this was the equipment actually installed and qualified.

The organization should be able to show:

URS → Approved Design → FAT/SAT → Equipment Identification → IQ → OQ/PQ

Another question:

How do you know this instrument was calibrated when OQ was executed?

Expected evidence:

  • instrument ID;
  • calibration certificate;
  • calibration date;
  • due date;
  • IQ instrument register;
  • OQ execution date.

9.87 Inspector Question — Software

An inspector may ask:

Which software version was qualified?

A strong answer should identify:

PLC Version + HMI Version + SCADA Version + Relevant Firmware/Configuration + Controlled Backup

If the organization cannot identify the qualified software baseline, maintaining the qualified state becomes difficult.


9.88 Inspector Question — As-Built Drawing

An inspector may select a P&ID and ask:

Show me this line and these instruments in the field.

If the actual installation materially differs from the controlled drawing, the inspector may question:

  • engineering change control;
  • qualification accuracy;
  • maintenance controls;
  • calibration coverage;
  • system knowledge.

Therefore:

As-built accuracy is a GMP lifecycle control, not merely an engineering housekeeping exercise.


9.89 Inspector Question — Product-Contact Material

An inspector may ask:

How did you establish that this product-contact component is the specified material?

A robust evidence chain is:

URS/Design Requirement

Approved Material Specification

Vendor Certificate

Component Identification

IQ Verification

Controlled Record


9.90 Maintaining the IQ Baseline

IQ should not be considered a one-time historical document disconnected from future operation.

After qualification, changes to the installed baseline may require assessment.

Examples:

  • motor replacement;
  • PLC replacement;
  • instrument replacement;
  • software upgrade;
  • network change;
  • new product-contact component;
  • utility modification.

These should enter:

Change Control → Risk Assessment → Qualification Impact Assessment → Required Verification → Updated Baseline


9.91 Like-for-Like Replacement

Even a claimed “like-for-like” replacement should be evaluated according to the site’s change/maintenance procedure.

Consider:

  • manufacturer;
  • model;
  • material;
  • range;
  • accuracy;
  • firmware;
  • configuration;
  • function.

A replacement should not be assumed equivalent merely because it physically fits.


9.92 Requalification Trigger

Changes to IQ-established attributes may trigger partial requalification.

Examples:

Instrument Replacement

Potential:

  • IQ verification;
  • calibration;
  • affected OQ function.

PLC Upgrade

Potential:

  • software/configuration verification;
  • regression testing;
  • OQ.

Product-Contact Material Change

Potential:

  • IQ;
  • cleaning assessment;
  • process/quality risk assessment.

The extent should be risk based.


9.93 IQ Documentation Hierarchy

A strong IQ package may contain:

IQ Protocol
   │
   ├── Equipment Identification
   ├── Installation Records
   ├── Component Register
   ├── Material Certificates
   ├── Instrument Register
   ├── Calibration Certificates
   ├── Utility Records
   ├── Electrical Records
   ├── Software Baseline
   ├── Drawings
   ├── As-Built P&IDs
   ├── Vendor Documentation
   ├── Deviations
   ├── Raw Evidence
   └── IQ Summary Report

9.94 Good Documentation Practices During IQ

IQ execution should follow applicable GDP requirements.

Ensure entries are:

  • attributable;
  • legible;
  • contemporaneous;
  • original/true copy as applicable;
  • accurate;
  • complete;
  • consistent;
  • enduring;
  • available.

Avoid:

  • blank fields;
  • undocumented corrections;
  • backdating;
  • pencil where prohibited;
  • unexplained overwriting;
  • copied results;
  • untraceable attachments.

9.95 Handling Corrections

If an execution error is made in a paper record, corrections should follow approved GDP procedures.

The original entry should remain readable.

Electronic corrections should similarly maintain appropriate traceability.

Qualification data should never be manipulated to make a failed test appear to have passed initially.


9.96 Photographic Evidence

Photographs can support IQ for:

  • equipment nameplates;
  • component identification;
  • installation;
  • utility connections;
  • labels;
  • safety devices.

However:

A photograph should support controlled verification, not replace the protocol’s documented assessment.

Photos should be identifiable and traceable to the relevant test where used.


9.97 IQ Inspection-Readiness Checklist

Protocol

  • □ Approved IQ protocol
  • □ Defined objective
  • □ Defined scope
  • □ Responsibilities assigned
  • □ Acceptance criteria established

Equipment

  • □ Name
  • □ Tag
  • □ Manufacturer
  • □ Model
  • □ Serial number
  • □ Location
  • □ Orientation
  • □ Leveling/anchoring where relevant

Components

  • □ Major components
  • □ Product-contact parts
  • □ Materials
  • □ Surface finish where specified
  • □ Gaskets/seals where significant

Utilities

  • □ Electricity
  • □ Compressed air
  • □ Vacuum
  • □ Dust extraction
  • □ Water/steam/process utilities where applicable
  • □ Connections
  • □ Identification

Piping

  • □ P&ID verified
  • □ Line identification
  • □ Flow direction
  • □ Valves
  • □ Instruments
  • □ As-built status

Electrical

  • □ Panel
  • □ Supply
  • □ Wiring
  • □ Protection
  • □ Motors
  • □ Drives
  • □ Earthing
  • □ Drawings

Instrumentation

  • □ Instrument register
  • □ Tags
  • □ Manufacturer/model
  • □ Range
  • □ Accuracy where required
  • □ Calibration
  • □ Due dates
  • □ Calibration range suitability

Automation

  • □ PLC hardware
  • □ PLC software
  • □ HMI
  • □ SCADA where applicable
  • □ Firmware
  • □ Software versions
  • □ Configuration baseline
  • □ Backup
  • □ Network
  • □ Interfaces

Safety

  • □ Guards
  • □ Emergency stops
  • □ Safety switches
  • □ Safety relays
  • □ Pressure-relief devices where applicable

Lifecycle

  • □ Manuals
  • □ Spare parts
  • □ Lubricants
  • □ PM requirements
  • □ Calibration requirements
  • □ SOP requirements
  • □ Training requirements
  • □ Equipment status controls

Documentation

  • □ GA drawing
  • □ Layout
  • □ P&ID
  • □ Electrical drawings
  • □ Instrument list
  • □ Component list
  • □ Material certificates
  • □ Calibration certificates
  • □ Software records
  • □ As-built documents

Closure

  • □ All tests executed
  • □ Actual results recorded
  • □ Evidence traceable
  • □ Deviations documented
  • □ Failed tests retained
  • □ Retests controlled
  • □ Open items assessed
  • □ Critical issues closed
  • □ IQ summary completed
  • □ OQ readiness approved

9.98 IQ Readiness Decision Tree

IQ Execution Complete
        ↓
Any Critical Failure?
   ┌────┴────┐
  Yes        No
   │          ↓
Hold OQ   Open Items?
   │       ┌──┴──┐
Correct   Yes    No
   │       │      │
Retest  Assess   ↓
   │     Impact  IQ Approved
   │       │      │
   └───────┴──────┘
           ↓
       OQ Readiness

9.99 Golden Rule of Installation Qualification

The strongest IQ principle is:

Do not qualify what the drawing says should be installed. Qualify what is actually installed—and ensure the controlled documentation accurately represents that final installed state.

IQ should establish an objective, traceable baseline linking:

Design → Equipment → Components → Materials → Utilities → Instruments → Calibration → Automation → Software → Safety → Documentation → As-Built Configuration


9.100 Part 9 — Key Takeaway

Installation Qualification is the formal lifecycle stage that transforms a delivered and site-accepted system into a documented qualified installation baseline.

A robust IQ establishes:

1. Identity

The correct equipment and critical components are installed.

2. Physical Installation

Location, orientation, assembly and connections correspond to approved requirements.

3. GMP Construction

Product-contact materials and other critical construction attributes are documented.

4. Utilities and Electrical Systems

Required services are appropriately installed and connected.

5. Instrumentation

Critical instruments are identified and have appropriate calibration status.

6. Automation Baseline

PLC, HMI, SCADA, firmware, software, network and relevant configuration are documented.

7. Safety

Required safety devices are physically installed.

8. Lifecycle Controls

Maintenance, calibration, SOP, training, spare-parts and documentation requirements are established.

9. As-Built Accuracy

Controlled engineering documentation represents the actual installed system.

10. OQ Readiness

Critical installation deficiencies are resolved before functional qualification begins.

The final evidence chain is therefore:

URS → Risk Assessment → DQ → FAT → SAT → IQ Installed Baseline → OQ Functional Verification → PQ Performance Verification → Qualification Summary → GMP Release

Part 10 — Operational Qualification (OQ) is the next stage. It should move from verifying what is installed to challenging how the installed system actually operates, including operating ranges, upper/lower limits, alarms, interlocks, sequences, controls, failure modes, recovery, recipes, user access, audit trails, electronic records, backup/restore and computerized-system functions, with strong emphasis on worst-case and boundary testing, objective evidence, deviation handling, and risk-based traceability.

About the Author

Ramesh Palav is a pharmaceutical professional with 20+ years of industry experience in manufacturing, GMP, quality systems, validation, compliance, and operational excellence. Through Pharma Manufacturing Hub, he shares practical insights on pharmaceutical careers, manufacturing, quality, validation, Pharma 4.0, AI, and professional development.

His goal is to help students, freshers, experienced professionals, and career-break professionals build the knowledge and skills needed to succeed in the pharmaceutical industry.

Leave a Comment

Scroll to Top